Recently
ALCO has terminated the handling works of the elements of the structure, the supply silos, and the new furnace installed by
Hidronitro Española in their installations in Monzón which will enable them to increase their production.
The works required a great deal of
synchronisation and complete precision. The assembly was carried out inside the factory, in a very small area and taking advantage of the times between castings as one of the determinants was
not to stop the daily production. Taking into consideration that in every discharge of the melts the
temperature exceeds
For the assembly, which was supervised on site by
ALCO's
own prevention serviceown prevention service, the technicians from the mobile crane's department chose the
liebherr 1100, that with maxim operative loading capacities of 100 T and
Besides from the furnace installation,
ALCO's Mobile Cranes continue to work at Hidonitro in the tasks of
extension of the installations carried out in the foundry which is located in the